Electrical work is labour-heavy, and it happens in phases. The risk is that rough-in quietly uses up hours that were meant for trim, and nobody notices until the last week. JobFigure puts crew hours on the job as they happen, so you can check labour at the end of each phase.

What electrical contractors track in JobFigure

Set up for electrical from the first day

When you pick Electrical as your trade, JobFigure loads these cost categories for budgets, receipts, and job costs. You can rename or add your own at any time.

Bid line items use the units electrical actually bid in: metres (m), each (EA), and lump sum (LS).

Example: what a electrical job looks like mid-way

Rough-in is complete and trim-out starts next week. Fixtures haven’t been bought yet.

Office renovation: contract $111,000
Cost categoryBudgetSpent so far
Materials$24,000$22,200
Labour$45,000$32,400
Fixtures$16,500$0
Equipment Rental$2,250$1,350
Permits$1,200$1,200
Other$1,800$750
Total$90,750$57,900

Labour is 72% spent at the end of rough-in. If you planned rough-in at about 60% of your labour, trim starts 12 points behind. Now is the time to plan the crew for trim, or find the variation that explains the extra hours.

Invoices the Australian way

Set your company to Australia and every progress invoice is a GST tax invoice with your ABN and retention. Tick one box to make it a payment claim under your state’s security of payment Act, and at year end the TPAR report totals what you paid each contractor. Prices are in Australian dollars. More in our guide: Payment claims under Australia’s security of payment laws.