On a solar job, the equipment is bought up front and the margin is made in the field: how fast racking and panels go on, how long the lift stays, and whether interconnection drags. JobFigure keeps equipment and field costs apart, so the job’s real progress isn’t hidden behind the panel invoice.

What solar installers track in JobFigure

Set up for solar from the first day

When you pick Solar as your trade, JobFigure loads these cost categories for budgets, receipts, and job costs. You can rename or add your own at any time.

Bid line items use the units solar actually bid in: kilowatts (KW), each (EA), square metres (m²), and lump sum (LS).

Example: what a solar job looks like mid-way

Ballasted racking and about 560 panels on a flat roof. The racking is done, the panels are about 60% set, and the electrical tie-in is still ahead.

250 kW rooftop system, distribution warehouse: contract $618,000
Cost categoryBudgetSpent so far
Panels & Inverters$252,000$252,000
Racking & Mounting$69,000$67,200
Labour$108,000$61,500
Electrical Materials$42,000$14,700
Permits & Interconnection$13,500$9,750
Equipment Rental$21,000$13,650
Other$9,000$2,550
Total$514,500$421,350

Panels and racking were bought up front, so they’re fully spent, as expected. Labour is 57% spent with the racking done and panels about 60% set, which is on pace. The lift rental, at 65%, is worth watching: it has to stay through the last 40% of the panels.

Invoices the Australian way

Set your company to Australia and every progress invoice is a GST tax invoice with your ABN and retention. Tick one box to make it a payment claim under your state’s security of payment Act, and at year end the TPAR report totals what you paid each contractor. Prices are in Australian dollars. More in our guide: Payment claims under Australia’s security of payment laws.