Job costing for landscaping contractors
Landscape installs have thin margins and lots of moving parts: plant material, sod, irrigation, rentals, and crews who bounce between jobs. JobFigure keeps plants and sod on their own line and puts every crew hour on the right job.
What landscaping contractors track in JobFigure
- Plants and sod separately. Nursery and sod invoices post to their own budget, apart from mulch, stone, and irrigation parts.
- Crews that move between jobs. Crews clock in at each site on their phones, so a day split across three jobs is costed correctly.
- Scope by area. Line items like “Sod, 6,500 SY” or “Shrubs, front beds” become the job’s scope, and progress is logged by quantity.
- Quotes accepted online. Homeowners and property managers can accept a quote from a private link, and the bid turns Won.
Set up for landscaping from the first day
When you pick Landscaping as your trade, JobFigure loads these cost categories for budgets, receipts, and job costs. You can rename or add your own at any time.
- Materials
- Labour
- Plants & Sod
- Equipment Rental
- Fuel
- Dump Fees
- Subcontractor
- Other
Bid line items use the units landscaping actually bid in: square feet (SF), square yards (SY), cubic yards (CY), each (EA), and lump sum (LS).
Example: what a landscaping job looks like mid-way
Grading, irrigation, 210 trees and shrubs, mulch beds, and 6,500 square yards of sod. The irrigation and plantings are done; the sod goes down next week.
| Cost category | Budget | Spent so far |
|---|---|---|
| Plants & Sod | $70,200 | $45,090 |
| Labour | $51,300 | $37,660 |
| Materials | $24,300 | $21,060 |
| Equipment Rental | $9,450 | $6,880 |
| Fuel | $4,050 | $2,970 |
| Dump Fees | $2,030 | $1,080 |
| Other | $2,700 | $680 |
| Total | $164,030 | $115,420 |
Plants and sod at 64% looks right, with the sod, the rest of that budget, still to come. Labour is the tight one: 73% is spent, and laying 6,500 square yards of sod takes a lot of labour. On a job with margin this thin, put the full crew on the sod and get it down in as few days as possible.
Invoices the Canadian way
Set your company to Canada and each invoice applies GST, HST, or GST plus PST or QST for the province where the work is, and tracks the 10% holdback. At year end, the subcontractor payments report gives you the totals for T5018 slips. Prices are in Canadian dollars. More in our guide: GST/HST, PST and holdback on construction invoices in Canada.
Guides and tools for landscaping contractors
GST/HST, PST and holdback on construction invoices in Canada
Canada: sales tax by province, PST on construction, the 10% holdback, and T5018 slips.
GuideGPS time clocks for construction crews: a practical guide
What GPS clocks fix, how they work, and what to watch for: notice, privacy, drive time, overtime.
GuideHow to follow up on a construction bid and win more work
A follow-up schedule, what to say, and using your win rate to pick which jobs to bid.