Job costing for plumbing contractors
A plumbing job runs in stages (underground, top-out, trim), often weeks apart, with other trades in between. Costs spread out over months are easy to lose track of. JobFigure keeps every receipt and crew hour on the job, so the margin is current when you come back for the next stage.
What plumbing contractors track in JobFigure
- Stages as scope lines. Bid underground, top-out, and trim as separate lines, and they carry over to the job’s scope.
- Fixtures separately from rough materials. Owner fixture selections change. Keeping fixtures in their own category makes those changes easy to spot and bill.
- Crew hours across a long schedule. Hours post to the job whenever the crew is on it, even months apart.
- Permits and inspections tracked as costs, not forgotten.
Set up for plumbing from the first day
When you pick Plumbing as your trade, JobFigure loads these cost categories for budgets, receipts, and job costs. You can rename or add your own at any time.
- Materials
- Labour
- Fixtures
- Equipment
- Permits
- Fuel
- Subcontractor
- Other
Bid line items use the units plumbing actually bid in: metres (m), each (EA), and lump sum (LS).
Example: what a plumbing job looks like mid-way
Underground and top-out are complete; trim is waiting on fixtures.
| Cost category | Budget | Spent so far |
|---|---|---|
| Materials | $20,620 | $17,980 |
| Labour | $34,650 | $21,620 |
| Fixtures | $15,680 | $0 |
| Equipment | $2,970 | $2,800 |
| Permits | $1,160 | $1,160 |
| Other | $1,650 | $580 |
| Total | $76,730 | $44,140 |
Rough materials and labour are in line, with 62% of labour used and trim still ahead. The open question is fixtures: nothing bought yet. If the owner upgrades selections, write the variation before you order, not after.
Invoices the New Zealand way
Set your company to New Zealand and every progress invoice is a GST tax invoice with retentions. Tick one box to make it a payment claim under the Construction Contracts Act 2002, with the statement, work period and due date it needs. Prices are in New Zealand dollars. More in our guide: Payment claims under the Construction Contracts Act 2002.
Guides and tools for plumbing contractors
Payment claims under the Construction Contracts Act 2002
New Zealand: the six things a payment claim must include, Form 1, and the 20-working-day payment schedule.
GuideJob costing for contractors: a step-by-step guide
What counts as a job cost, and a six-step system to know what every job made before it’s over.
GuideHow to follow up on a construction bid and win more work
A follow-up schedule, what to say, and using your win rate to pick which jobs to bid.