On a solar job, the equipment is bought up front and the margin is made in the field: how fast racking and panels go on, how long the lift stays, and whether interconnection drags. JobFigure keeps equipment and field costs apart, so the job’s real progress isn’t hidden behind the panel invoice.

What solar installers track in JobFigure

Set up for solar from the first day

When you pick Solar as your trade, JobFigure loads these cost categories for budgets, receipts, and job costs. You can rename or add your own at any time.

Bid line items use the units solar actually bid in: kilowatts (KW), each (EA), square metres (m²), and lump sum (LS).

Example: what a solar job looks like mid-way

Ballasted racking and about 560 panels on a flat roof. The racking is done, the panels are about 60% set, and the electrical tie-in is still ahead.

250 kW rooftop system, distribution warehouse: contract $679,800
Cost categoryBudgetSpent so far
Panels & Inverters$277,200$277,200
Racking & Mounting$75,900$73,920
Labour$118,800$67,650
Electrical Materials$46,200$16,170
Permits & Interconnection$14,850$10,720
Equipment Rental$23,100$15,020
Other$9,900$2,800
Total$565,950$463,480

Panels and racking were bought up front, so they’re fully spent, as expected. Labour is 57% spent with the racking done and panels about 60% set, which is on pace. The lift rental, at 65%, is worth watching: it has to stay through the last 40% of the panels.

Invoices the New Zealand way

Set your company to New Zealand and every progress invoice is a GST tax invoice with retentions. Tick one box to make it a payment claim under the Construction Contracts Act 2002, with the statement, work period and due date it needs. Prices are in New Zealand dollars. More in our guide: Payment claims under the Construction Contracts Act 2002.